Wazzup Pilipinas!
Contrary to recent reports of delays in the re-tender of the country’s largest railway Public-Private Partnership (PPP) project, the Department of Transportation and Communications (DOTC) is expediting the bidding process for the improved P 65 Billion Light Rail Transit Line 1 Cavite Extension (LRT-1 Cavex) Project.
“The only delay was in the schedule of the NEDA Board meeting. Otherwise, we are still following the same 4- to 6-month timeline from obtaining approval to set the bid submission deadline,” said DOTC Spokesperson Michael Arthur Sagcal.
“In fact, we are expediting it. We will adopt the single-stage bidding process, and we will set the bid submission date in the earlier part of Q2 2014,” Sagcal added.
The single-stage bidding process means that interested groups will submit their qualification documents simultaneously with their technical and financial proposals, instead of having a separate pre-qualification phase. This will do away with the two-stage process, effectively cutting the entire period by around two (2) months.