The Manila International Airport Authority (MIAA), with the assistance of power distributor Manila Electric Co. (Meralco), has started on Friday, May 5 the electrical audit of the Ninoy Aquino International Airport (NAIA) Terminal 3.
The audit is expected to be completed in three weeks, according to MIAA Officer-in-Charge Bryan Co.
Co added that once the audit is concluded, the MIAA will be able to determine the various equipment needed to be upgraded, rehabilitated or purchased to make NAIA Terminal 3’s power system reliable and resilient.
The MIAA will then determine the timeline as well as the required budget for the procurement of critical components of its electrical facilities, generator sets, and implement the necessary power systems upgrade at Terminal 3.
“Yes, kailangan naming bumili or mag lease ng additional generators and we are discussing with stakeholders and that’s the time na madetermine kung magkano ang kailangang budget,” said Co.
As an immediate move, the MIAA is exploring the option of leasing generator sets to increase the capacity of Terminal 3's back-up power.
The audit is expected to assist MIAA in ensuring reliability of its power supply and prioritize major components for the system upgrade of its existing electrical facilities.
In Brisbane's northside, Buffalo Air & Electrical is a well-known electrical and air conditioning company. Brisbane A/C repair's staff is qualified to handle any size project. You can check them out here. They differentiate themselves in a competitive market by providing rapid, trustworthy, and clean services delivered by properly licenced, insured, and certified employees.