Wednesday, January 20, 2021

Bicol International Airport construction overall progress rate now at 72.2 percent



Wazzup Pilipinas!

Construction of the Bicol International Airport (BIA), which is touted as the “Most Scenic Gateway” in the country, is moving at a fast pace.

At present, construction work at the BIA has been logged at 72.2 percent overall progress rate, considering that actual construction of the airport only started in December 2016.

As of 13 January 2021, Package 2A of the BAI development project is now 88.2 percent complete.

Construction work in Package 2A is being handled by the Sunwest Construction and Development Corp. and covers the airport’s landside facilities, such as the Administration Building, Air Traffic Control Building, Crash Fire Rescue Building, and the Maintenance Building.

Package 2B of the airport project, meanwhile, is now 49.5 percent complete. Package 2B which is being handled by the E.M. Cuerpo construction company, covers the construction of the passenger terminal building (PTB), taxiway, runway extension, and other site development works.








Once completed, the BIA, which features the iconic Mayon Volcano as its magnificent backdrop, is expected to serve a total of 2 million airline passengers every year. The new international airport is also projected to boost air traffic in the region amid the existing coronavirus disease 2019 (COVID-19) pandemic.

The BIA initially started construction in 2008. However, development works were uncompleted until 2012. When the Duterte administration came in 2016, the airport's Package 2A and 2B projects were continued.

An important component of the Duterte Administration’s “Build, Build, Build” Program, the BIA also intends to be an instrumental in the transformation of Albay Province, and the rest of the Bicol Region, into a strong economic contender.

Secretary Tugade stressed the importance of having continuous transport infrastructure developments such as the BIA, which will prove vital as the country starts recovering from the impact of COVID-19.

“It can’t be denied that the aviation sector has been one of the hardest hit by the pandemic. That’s why it is important that we finish the airport at the soonest possible time, as this will absolutely give the economy a boost. Gusto ko matapos ‘yan within the year dahil gusto na natin itong agad na mapakinabangan ng ating mga kababayan. As we ready for take-off, kung baga, dapat all systems go,” the transportation chief emphasized.

3 comments:

  1. Hookup culture has become an hookupguide accepted style of human connection. The desire to have sex without strings attached has always been a thing, but proudly searching for just that is just way less taboo than it was when your parents were dating.

    ReplyDelete
  2. Another popular choice is the Wagner Control Pro 170 High-Efficiency Airless Sprayer, which offers a smooth and consistent finish with minimal overspray. With its lightweight design and adjustable pressure settings, it is a great choice for both professionals and DIYers alike. Ultimately, the airless paint sprayer Los Angeles will vary depending on individual needs and preferences, but these top options are surely worth considering for anyone looking for reliable and efficient painting equipment.

    ReplyDelete
  3. I often see your posts. I love this so let me share with you that corinth deck builder takes pride in their attention to detail and commitment to delivering high-quality workmanship in every project. Whether it's a cozy backyard oasis or a spacious multi-level deck, their goal is to create functional and beautiful outdoor spaces that homeowners can enjoy for years to come.

    ReplyDelete